Hollister/U.S. 65 Interchange
Construction
Update for Week of July 11
Work scheduled:
* Rock blasted at various times each day along U.S. 65 near Route
165
* Construction of new bridge over U.S. 65 -- interchange bridge
-- along existing lanes
* Concrete poured for curb and barrier wall near Gage Drive
* Grading and utility relocation on Blue Sky Lane
* Concrete poured for curb and gutter and signal installation
near Industrial Boulevard and Birch Road
* Drain pipe installation along Route V near College of the Ozarks
Impact on Traffic:
* Two-way traffic on U.S. 65 shifted to temporary bypass (new
northbound lanes) east of existing lanes
* U.S. 65 traffic stopped periodically about 5 minutes at a time
for blasting near roadway
* Heavy equipment near roadway and trucks entering/leaving construction
areas on Route V and Gage Drive west of U.S. 65
* Occasional one-lane traffic on Blue Sky Lane
* Occasional one-lane traffic on Industrial Boulevard and Birch
Road
Most work taking place AWAY from traffic
Note: Large trucks and other vehicles
towing trailers should use Birch Road to access shopping center
because turning radius at Mall Road is tighter
Work zone speed limit on U.S. 65 Temporary Bypass: 35 mph.
Project background:
* Construction of U.S. 65/Business 65 interchange and separate
"flyover" bridge for Business 65 north of new interchange
* Widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet
north of Bus. 65/Route V to just south of Route 165)
* Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County
* Prime contractor: W.A. Ellis Construction of Independence
* Scheduled completion: Fall 2006
(For more information, call MoDOT in Springfield at 417-895-7600