Hollister/U.S. 65 Interchange
Construction
Update for Week of September 5
No work planned over the Labor Day Holiday weekend.
It may be necessary to close U.S.
65 for short periods during one night. When the nightwork schedule
is determined, a special Traffic Alert! will be sent out.
Work scheduled:
* Rock blasted two to three times each day along U.S. 65 near
Gage Drive in area of interchange construction
* Concrete poured for curb and gutter and traffic signal bases
near Industrial Boulevard and Birch Road
* Drain pipe installation, dirt grading and traffic signal installation
along Route V near College of the Ozarks
* Construction of new Business 65 overpass bridge
Impact on Traffic:
* U.S. 65 traffic stopped about 5 minutes at a time for blasting
near roadway
* Two-way traffic on U.S. 65 shifted to temporary bypass (new
northbound lanes) east of existing lanes
* Heavy equipment near roadway and trucks entering/leaving construction
areas on Route V and Gage Drive west of U.S. 65
* Short traffic stops on Route 165 west of College of the Ozarks
* Occasional one-lane traffic on Industrial Boulevard and Birch
Road
Most work taking place AWAY from traffic
Note: Large trucks and other vehicles
towing trailers should use Birch Road to access shopping center
because turning radius at U.S. 65 and Mall Road is tighter
Work zone speed limit on U.S. 65 Temporary Bypass: 35 mph.
Project background:
* Construction of U.S. 65/Business 65 interchange and separate
overpass bridge for Business 65 north of new interchange
* Widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet
north of Bus. 65/Route V to just south of Route 165)
* Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County
* Prime contractor: W.A. Ellis Construction of Independence
* Scheduled completion: Fall 2006
(For more information, call MoDOT in Springfield at 417-895-7600
or toll-free at 1-888-ASK-MoDOT.)