All road work listed below is subject to change due to weather or priority adjustments.

map Scotland Clark Knox Lewis Shelby Marion Monroe Ralls Pike Audrain Montgomery Lincoln warren Counties:

If you have questions about MoDOT's work schedule, please call customer service toll-free at 1-888-275-6636 during normal business hours, or email us directly customerservice3@modot.org.

eupdateSubscribe to MoDOT's free e-update service to

receive information about projects through email.

 

All offices will be closed Friday, July 3 in observance of Independence Day

All construction jobs will close down for Independence Day weekend on noon Thursday, July 2 and will be back in operation on Monday, July 6 at 9 a.m.

 

Audrain County
Construction Projects

Route 54 - J.C. Industries, Inc., Job #J3P2170 - Grading and paving to add sweeping offset right turn lane and remove westbound right turn lane.

Location:  Route 19 intersection near Scotts Corner east of Mexico

Work Zone Info: The majority of the work on the Scott’s Corner project is off of the main roadway and motorists should not be directly affected by the construction, however commuter parking will be limited to the west half of the roadside park during construction. Contractor working 4-10 hour days.

Project Status:  25% complete - Contractor will be working on base rock this week. There should be little to no traffic disruption during this process. Commuter parking will be limited to the west half of the roadside park during construction.

Estimated Completion:  August 2009

Route 15  APAC-Missouri, Inc., Job #J3S2178 - Resurfacing 24.3 miles in Audrain and Monroe Counties - Economic Recovery Project/Ready to Go

Location: Resurfacing from 1.1 miles north of Route 22 to 0.2 mile north of Route 54 at Mexico, 5 miles-News Release

Work Zone Info: Project inactive - One lane traffic at the work zone

Project Status: 0% complete - Project inactive

Estimated Completion:

Maintenance

South Clark St. (Mexico) & Route 15 - July 6-9 hot-mix patching, short-term lane closures with flaggers.

Routes 19 & 54 - July 6-9 repairing road joints, intermittent lane closures with flaggers.

Route E - July 13-16 cold mix patching, short-term lane closures with flaggers.

Audrain County Home Page

Future Construction Projects for Audrain County

Back to Top

Callaway County

Maintenance

 

Clark County
Construction Projects

Route 61/27 - Chester Bross Const. Job #J3P0728 - Rehabilitate pavement at 5 disconnected sections

Location:  From Iowa line to south of Route 136 spur at Lewis County line, 12.98 miles-News Release Project Awarded

Work Zone Info:  Project inactive

Project Status:  0% complete - Project inactive

Estimated Completion:  November 2009

Route 61 - Avenue of the Saints Completed - Opened to traffic 07-25-08.

See Avenue of the Saints Project Webpage

Maintenance

Route 61 – July 6-9, working southbound driving lane at Mound Roadside Park from 7 a.m. to 4 p.m.; traffic reduced to one lane approx. 9 miles south of Wayland.

Route 136 - July 6-9 concrete patching from ½ east of Kahoka west approx. 4 miles; traffic will be reduced to one lane during the day while the work is being performed and will remain one lane until approximately 7-8 p.m. to allow adequate drying time for the concrete.  Minor delays should be expected.

Route 61 – July 8 concrete patching in southbound driving lane approx. 7 miles south of Wayland and at Honey Creek Bridge; traffic will be reduced to one lane during the day while the work is being performed and will remain one lane until approximately 7-8 p.m. to allow adequate drying time for the concrete.  Minor delays should be expected.

Route NN - July 13-16 hand patching between Routes AA and K, moving operation.

Clark County Home Page

Future Construction Projects for Clark County

Back to Top

Knox County
Construction Projects

Route C - Boone Construction Job#J3B0801B - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  North Fork South Fabius River near Greensburg - Picture of Completed Bridge

Work Zone Info:  OPEN TO TRAFFIC MAY 13, 2009.

Maintenance
Route 15 – July 6-16 chip seal from Edina to Route 136 in Scotland County and back to Route 168 in Shelby County. Traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Route 6 – July 15-23 chip seal from Route 15 in Edina and west to Route 61 in Marion County, approximately 41 miles; traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Knox County Home Page

Future Construction Projects for Knox County

Back to Top

Lewis County

Construction Projects

Route 61/24 - Chester Bross Const. Job #J3P0773 - Rehabilitate pavement and shoulders.

Location:  From north of Route B near LaGrange to south of Route 6 in Marion County-News Release Project Awarded

Work Zone Info:  Traffic will be reduced to one lane at the work zone.

Project Status:  47% complete - Laying asphalt on Route 61/24 westbound and eastbound and Route 61 northbound lanes; also laying top lift of asphalt on mainline. Installing guardrail on Route 61 northbound and southbound lanes.

Estimated Completion:  November 2009

Route E - Pace Const. Job #J3B0801E - Redecking bridge at Wyaconda River (Includes Monroe Route C at Elk Fork Salt River)- Safe & Sound Bridge Project

Location:  Wyaconda River between Route F and Route 81-News Release Project Awarded

Work Zone Info:  Project inactive - Road will be closed at the bridge beginning mid-July

Project Status:  0% complete - Project inactive, tentatively scheduled to begin work and close bridge mid-July.

Estimated Completion:  November 2009

Maintenance

Routes A and E - July 6-8 drainage work, moving operation.

Route 15 - July 6-9 chip sealing, one lane closure with signs and flaggers.

Route 15 - July 13-16 chip sealing, one lane closure with signs and flaggers.
Route 16 - July 14-15 shoulder and approach repair, moving operation.|
Route 6 – July 15-23 chip seal from Route 15 in Edina and west to Route 61 in Marion County, approximately 41 miles; traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Lewis County Home Page

Future Construction Projects for Lewis County
Back to Top

Lincoln County

Construction Projects

Route 61 - Iron Mountain Trap Rock Co. Job# J3P2146/J3P2146C Construct an interchange between Route U and Mette Road on Route 61; partnership agreement between MoDOT and Crossroad Centers, Inc. The work involves building a new bridge over Route 61 to carry Route U and Mette Road traffic. Ramps will be built to allow traffic off of and on to Route 61.

Location: Route 61, U and Mette Road just south of Moscow Mills-News Release Project Awarded

Work Zone Info:  One lane traffic and short-term daytime lane closures are possible.

Project Status:  Project 32% complete - Utility work, drainage and related grading to continue. Bridge substructure work in progress and wall work at Bent 1 to continue.

Estimated Completion: September 2010

Route DD - Bleigh Construction Job#J3B0801D - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  Bear Creek-News Release Safe & Sound Project Awarded

Work Zone Info:  Project active - Road closed at the bridge May 18, scheduled to open to traffic July 31.

Project Status:  25% complete - Contractor will place and tie rebar and pour deck.

Estimated Completion:  August 2, 2009

Route J - G & M Concrete & Asphalt Job #1S2009S (Includes Warren County) Resurfacing - Economic Recovery Project/Ready to Go

Location: from Route 47 to Interstate 70 North Outer Road in Warren County, 11.6 miles-News Release

Work Zone Info: One lane traffic at work zone with flaggers during daytime work hours.

Project Status: Project 0% complete - Project inactive, work scheduled to begin July 20.

Estimated Completion:

Route EE - G & M Concrete & Asphalt Job #1S2009Z - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from Route Y to Route 47, 5.3 miles-News Release

Project Status: Completed June 25.

Route KK - G & M Concrete & Asphalt Job #1S3009A - Resurfacing - Economic Recovery Project/Ready to Go

Location: from Old Route 61 to Route W, 6.4 miles-News Release

Work Zone Info: One lane traffic at work zone with flaggers during daytime work hours.

Project Status: Project 0% complete - Project inactive, work scheduled to begin July 6.

Estimated Completion:

Maintenance

Route EE - July 6 & 7 repairing edgeruts, moving operation with flaggers, daily 7 a.m to 4:00 p.m.

Route W - July 8 hot mix patching, one lane closed with flaggers.

Route D - July 9-13 hot mix patching, one lane closed with flaggers.

Routes TT & BB - July 14 & 15 hot mix patching, one lane closed with flaggers.

Route RA - July 16 hot mix patching, one lane closed with flaggers.

Lincoln County Home Page

Future Construction Projects for Lincoln County

Back to Top

Marion County
Construction Projects

Route 24 - Chester Bross Const. Job# J3P0785 - Pavement treatment, approx. 8.9 miles

Location:  From 1.1 miles west of Route J in Ralls County east to 0.9 mile east of Route H in Marion County - News Release Project Awarded

Work Zone Info:  Traffic reduced to one lane at the work zone, 45 mph through the work zone.

Project Status: 99% complete - Milling shoulders on passing lane from Route J near Monroe City to east of Route H near Hannibal.

Estimated Completion:  August 2009

Route 24/61 - Chester Bross Const. Job #J3P0773 - Rehabilitate pavement

Location:  From south of Route 6 to north of Route B near LaGrange in Lewis County-News Release Project Awarded

Work Zone Info:  Project active - One lane traffic at the work zone

Project Status:  10% complete - Laying asphalt on northbound and southbound lanes

Estimated Completion:  Fall 2009

Route 24 - Eagle Painting & Maint. Co. Job #J3P0752 - Cleaning and painting Quincy Bayview Bridge over Mississippi River

Location:  Two-lanes of westbound Highway 24 over the Mississippi River from Quincy, Illinois to West Quincy, Missouri

Work Zone Info: One lane of traffic will be closed with one lane remaining open at all times.

Project Status: 50% complete

Contact Info: This contract is the responsibility of Illinois Dept. of Transp., please contact 217-223-1380 for information.

Estimated Completion:  Late October 2009

See Route 36 Four-Lane Webpage

Maintenance

Route D - July 13 grader patching, one lane with flagger.

Route MM - July 14 and 15 grader patching, one lane with flagger.

Route OO - July 16 grader patching, one lane with flagger.

Route C – July 13-16 grader patching, one lane with flagger.

Route 61 – July 6-12 spraying for broadleaf control, moving operation with a follow truck.

Route E – July 13-16 grader patching, one lane with flagger.

Route EE - July 13-16 patching, moving operation.

Route 6 – July 15-23 chip seal from Route 15 in Edina and west to Route 61 in Marion County, approximately 41 miles; traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Marion County Home Page

Future Construction Projects for Marion County

Back to Top

Monroe County

Construction Projects

Route C - Pace Const. Job #J3B0801E - Redecking bridge at Elk Fork Salt River (Includes Lewis Route E at Wyaconda River)- Safe & Sound Bridge Project

Location:  Elk Fork Salt River between Route 24 and Route AA-News Release Project Awarded

Work Zone Info:  Project active - Road closed at the bridge from May 18 thru July 18

Project Status:  18% complete - Forming bridge deck and placing steel

Estimated Completion:  November 2009

Route 24 - CE Contracting Inc. - Job #J3P2148 - Slide correction on north and south sides of road

Location: 0.9 mile east of Route 154 and Route 24 near Paris

Work Zone Info:  Project - One lane traffic at the work zone from May 4 through July 20.

Project Status:  Project 80% complete- Excavating and placing rock in section 1 west of Route 15 along the south side and beginning work on north side.

Estimated Completion:  December 2009

Route 151 - Chester Bross Const. Job #1S3009B (Includes Shelby County) - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from Business Route 36 at Clarence to Route 24 at Madison, 22 miles-News Release

Work Zone Info: Project inactive - One lane traffic at the work zone

Project Status: 0% complete

Estimated Completion:

Route 15  APAC-Missouri, Inc., Job #J3S2178 (Includes Audrain County) - Resurfacing 24.3 miles in Audrain and Monroe Counties- Economic Recovery Project/Ready to Go - News Release

Location: Resurfacing from Route 154 north junction in Monroe County to 1.1 miles north of Route 22 at Mexico in Audrain County, 25 miles

Work Zone Info: Project inactive - Traffic will be reduced to one lane with a 10 ft. width restriction from 7 a.m. to 7 p.m. daily.

Project Status: Project inactive

Estimated Completion:

Maintenance

Route 107 - July 6 Chip seal east of Paris from Route 154 to Route 24; traffic will be reduced to one lane between 7 a.m. and 4:30 p.m. with a pilot car leading traffic through the work zone.

Route 154 - July 7 Chip Seal from Paris east approximately 6 miles; traffic will be reduced to one lane between 7 a.m. and 4:30 p.m. with a pilot car leading traffic through the work zone.

Routes 151 - July 6-9 cold mix patching, short-term lane closures with flaggers.

Routes 24 - July 13-16 repairing road joints, intermittent lane closures with flaggers.

Routes 15 - July 13-16 hotmix patching, short-term lane closures with flaggers.

Route 154 - July 6-8 bridge work at Elk Fork and South Fork Salt River Bridge east of Paris; one lane traffic from 8:30 a.m. to 4 p.m. daily.

Route 107 - July 9 bridge work at South Fork Salt River Bridge south of Route 154; one lane traffic from 8:30 a.m. to 4 p.m. daily.

Monroe County Home Page

Future Construction Projects for Monroe County

Back to Top

Montgomery County

Construction Projects

Interstate 70 - Lehman Const., Job# J3I0775 - Replace concrete pavement on the westbound lanes under the railroad overpass; existing pavement and base of the interstate will be removed and replaced with new and thicker base and concrete. Rumblestripes will be installed between the driving lanes and shoulders.

Location: East of Route F near High Hill-News Release Project Awarded

Work Zone Info:  Work zone area from Route E west to Route F south;May 17 crews will be striping, this is a moving operation, approximately 3 hours to complete. This job is very weather dependent and can be postponed several times.

Project Status:  Project 95% complete - May 17 beginning at 6 a.m. Crews will be striping concrete pavement on the westbound lanes under the railroad overpass just east of Route F near High Hill; this is a moving operation, approximately 3 hours to complete. This job is very weather dependent and can be postponed several times.

Estimated Completion: Fall 2009

Route F - Bleigh Construction Job#J3B0801D - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  Bear Creek-Picture of Completed Bridge

Work Zone Info:  OPEN TO TRAFFIC JULY 1, 2009.

Route AC - Bleigh Construction Job#J3B0801D - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  Cuivre River-News Release Safe & Sound Project Awarded

Work Zone Info:  Project inactive - Road will be closed at the bridge through Nov. 1

Project Status:  0% complete - Scheduled to begin August 17

Estimated Completion:  2009

SEE Missouri River Bridge at Hermann DEMOLITION WEBSITE

See Senator Christopher S. Bond Bridge Project Webpage

Maintenance

I-70 – July 7 expansion joint repair westbound at Loutre River Bridge; traffic will be reduced to one lane with a 12 ft. width restriction at the bridge during the day while the work is being performed, expect delays.

Route K - July 8 & 9 - chip sealing, lane closures using pilot car & flaggers.

Route 161 (from Middletown to Route 19) - July 15 & 16 chip sealing, lane closures using pilot car & flaggers.

Montgomery County Home Page

Future Construction Projects for Montgomery County
Back to Top

Pike County

Construction Projects

Route C - Don Schnieders Excavation Co. Job#J3B0801C - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  South Spencer Creek between Frankford and Vandalia.

Work Zone Info:  OPEN TO TRAFFIC JULY 1, 2009

Route 61 - Apparent low bidder Mid-River Asphalt, Inc. Job #J3P0776 - Diamond grind concrete pavement a rehabilitate shoulders on northbound and southbound lanes
Location: from 0.7 mile south of Route 161 south to 0.6 mile north of Route OO (3 disconnected sections)

Work Zone Info: Project inactive - Traffic will be reduced to one lane daily.

Project Status: Scheduled to begin mid to late August.

Estimated Completion: Fall 2009

Maintenance

US 61 - July 6-8 pothole patching, no closures, shoulder work only.

Business Route 61(Bowling Green) - July 8 drainage work/ditching, shoulder work with flaggers.

Various Routes - July 6-16 spraying herbicide & mowing, no closures, moving operation.

Pike County Home Page

Future Construction Projects fo Pike County

Back to Top

Ralls County

Construction Projects

Route P - Bleigh Construction Job#J3B0801D - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  Spencer Creek-News Release Safe & Sound Project Awarded

Work Zone Info:  Project inactive - Road will be closed at the bridge Sept. 8 thru Nov. 8.

Project Status:  0% complete - Scheduled to begin and road will officially close on Sept. 8.

Estimated Completion:  2009

Route V, T, N - G & M Concrete & Asphalt Co. - Job #J3M0048 - Pavement surface treatment

Location: from Bus. 61 to Route T, on Route T from Route N to Route V, and on Route N from Route T to Route 79, 8.79 miles

Work Zone Info:  Project inactive - Traffic will be reduced to one lane with a 10 ft. width restriction from 7 a.m. to 7 p.m. daily.

Project Status:  0% complete - Project inactive, work tentatively scheduled for mid-August.

Estimated Completion:  December 2009


Maintenance

Routes A, H and E – July 13-17 grader patching, one lane with flagger.

Ralls County Home Page

Future Construction Projects for Ralls County

Back to Top

Scotland County
Construction Projects

Route H - Boone Construction Job#J3B0801B - Rehabilitate bridge, Safe & Sound Bridge Project

Location:  Wyaconda River near Arbela - Picture of Completed Bridge

Work Zone Info:  OPEN TO TRAFFIC JUNE 30, 2009.

Maintenance

Route 15 – July 6-16 chip seal from Route 136 in Scotland County to Route 168 in Shelby County. Traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Scotland County Home Page

Future Construction Projects for Scotland County

Back to Top

Shelby County
Construction Projects

Route 36 - Progressive Contractors Job# J3P0409C & 410 - Grading and paving for new dual divided facility, minimal to no impact to traffic.

Location:  From 0.6 mile west of Route 15 at Shelbina east to 0.4 mile west of Ralls County at Monroe City

Work Zone Info: Most work off of traveled roadway. County Roads 467 and 473 at Route 36 closed until further notice. Several of these operations will be reduced speeds in areas with extra truck traffic entering and exiting various locations.

Project Status:  Project 55% complete - Shelby County area - Contractor will be working on erosion control maintenance, building temporary connections just east and west of the Salt River, which may require some brief periods of one-way traffic. There will be extra truck traffic entering and leaving the highway.

Marion County area - Contractor will be building temporary connections, grading roadway, erosion control and pipe work just west of Monroe City, which may involve some one-way traffic for brief periods. There will be extra truck traffic entering and leaving the highway.

Estimated Completion:  2010

See Route 36 Four-Lane Webpage

Route 36 - Bross Construction Job #J2P0482 - Grading, paving and concrete girder bridges for new dual divided facility.

Location:  From east of Route 63 near Macon to west of Route 15 near Shelbina

Work Zone Info:  Work off of traveled roadway, two-way traffic 60 mph, no restriction or lane closures at this time. Traffic on Route 36 will be detoured to the new Route 36 alignment just north of Clarence. There will be a three-way stop at the temporary intersection of Route 36 and Route 151. The Route 151 bridge over Route 36 will remain closed while the old bridge is removed and replaced with a longer structure. Detour signs will be in place to guide motorists through this area.

Project Status:  Project 50% complete - Macon/Shelby Counties - Contractor is continuing to install drainage structures at various locations throughout the project.  Construction of the Route 36 bridge over the Middle Fork of Salt River is complete as well as the Route 151 bridge over Route 36.  The Route 36 bridge over Crooked Creek is very near completion and construction of the Route 36 bridge over Route FF has begun.  Earthwork operations continue to move forward.  Additional subcontractor hired for earthwork from Lentner to Shelbina.  Traffic was switched onto the new lanes around Clarence on January 21, 2009 which allows removal and reconstruction of the Route 151 bridge over Route 36.


Estimated Completion:  July 2010 open to traffic; September 2010 completion.

See Route 36 Four-Lane Webpage

Route 151 - Chester Bross Const. Job #1S3009B (Includes Monroe County) - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from Business Route 36 at Clarence to Route 24 at Madison, 22 miles-News Release

Work Zone Info: Project inactive - One lane traffic at the work zone

Project Status: 0% complete

Estimated Completion:

Maintenance

Route N - July 6 grader patching, temporary lane closure.

Route FF - July 6-9 grader patching, temporary lane closure.

Route 15 south - July 6-9 grader patching, temporary lane closure.

Route 151 - July 8 grader patching, temporary lane closure.

Route H - July 9 grader patching, temporary lane closure.

Route 15 – July 6-16 chip seal from Route 136 in Scotland County to Route 168 in Shelby County. Traffic will be reduced to one lane between 7 a.m. and 4 p.m. with a pilot car leading traffic through the work zone.

Route D – July 15-16 grader patching, temporary lane closure.

Shelby County Home Page

Future Construction Projects for Shelby County

Back to Top

St. Charles County

Construction Projects

Route TT - G & M Concrete & Asphalt Job #1S2009X - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from Route 94 to Route T in St. Charles County, 3.6 miles-News Release

Work Zone Info:

Project Status: Project 0% complete - Project inactive, work scheduled to begin early July

Estimated Completion:

Warren County

Construction Projects

Interstate 70 - All Type Excavating Inc. (dba Krupp Const.) Job# J3I0774 - Rehabilitate pavement on westbound lanes

Location: From just west of Route 47 to the Montgomery county line, 7.24 miles - News Release Project Awarded

Work Zone Info:   Project inactive - One lane traffic at the work zone

Project Status:  Project 0% complete - Project inactive, work scheduled to begin July 27, 2009.

Estimated Completion: December 2009

Route J - G & M Concrete & Asphalt Job #1S2009S (Includes Lincoln County) - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from I-70 North Outer Road to Route 47 in Lincoln County, 11.6 miles-News Release

Work Zone Info:

Project Status: Project 0% complete - Project inactive, work scheduled to begin July 20.

Estimated Completion: Dec. 09

Route TT - G & M Concrete & Asphalt Job #1S2009X - Resurfacing - Economic Recovery Project/Ready to Go

Location: Resurfacing from Route 94 to Route T in St. Charles County, 3.6 miles-News Release

Work Zone Info:

Project Status: Project 0% complete - Project inactive, work scheduled to begin Late July

Estimated Completion:

Maintenance

Route D - July 6 hot mix patching, short-term lane closures with flaggers.

Route TT - July 7 hot mix patching, short-term lane closures with flaggers.

Route D - July 9 chip sealing, lane closures using pilot car & flaggers.

Route M - July 13 & 14 chip sealing, lane closures using pilot car & flaggers.