Route 54 (J3P0664, J3P0727, J3P0733)
- Improve intersection at Route 54 and 19 north junction at Basinger Corner
- Rehabilitate pavement from the Route 19 north junction to east to just west of Route P, approximately 7.93 miles
- Rehabilitate pavement from the Route 154 junction to Route U near Curryville, approximately 5.451 miles
- Pace Construction Co., LLC, St. Louis, MO
- Award Cost $4,596,400
- Project Manager – Rick Domzalski, 573-248-2579
|
|
Route 22 (J3P0726)
- Rehabilitate pavement and bridge from 0.1 mile west of Route E to west of Route 15, bridge over Davis Fork of Salt River, approximately 6.48 miles
- Chester Bross Construction Co., Hannibal, MO
- Award Cost $1,880,336.87
- Project Manager – Rick Domzalski, 573-248-2579
|
|