|
Because it is essential that MoDOT take care
of the more than 32,000 miles of highway on the state system,
rehabilitation and reconstruction of the existing roads is
a priority. Missourians agree; five times more Missourians
chose fixing the existing system as their top priority than
chose building new roads. In general, rehabilitation and reconstruction
activities are contracted and might include pavement resurfacing
and bridge and pavement replacement. It might also include
work that allows a roadway to meet desired standards, such
as the addition of shoulders or minor pavement or bridge widening.
It does not include activities that fundamentally change a
facility, like the addition of lanes.
Even working with the most optimistic
projections, MoDOT probably never would have the resources
to achieve 100 percent of the desired conditions established
for rehabilitation and reconstruction of pavement and bridges.
Establishing priorities that move toward meeting these expectations
is a more reasonable approach. After priorities are established,
associated goals and costs must be developed.
The National Highway
System, which includes the interstate system and other major
highways, will be MoDOT's first priority. This system represents
only 13 percent of the mileage, but carries more than 62 percent
of the traffic. Currently anticipated funding will not allow
MoDOT to achieve and maintain this system at 100 percent of
the desired pavement condition. Even if funds were available,
achieving this would be extremely difficult. MoDOT will
first take steps to stop the rate of deterioration on the
system, then reach and maintain a goal of 80 percent of the
system at the desired condition level.
Table
7
Highway Rehabilitation and Reconstruction Goals - NHS
(millions of dollars)
|
Attribute
|
Desired
Result
|
Mileage
Meeting Desired Result *
Current 80% Target
|
Cost
to Achieve
Desired
Result
(2000
dollars)
|
|
Pavement
|
PSR***
greater than or equal to 32
|
1,780 (42%)
|
3,389
|
$
2,544
|
|
Lane Width**
|
12'
travel lane
|
3,837 (90%)
|
|
0
|
|
Shoulder
|
10'
hard surface
|
2,013 (48%)
|
no goal
established
|
103
|
|
Total
|
|
$2,647
|
* Centerline miles - miles of highway measured down the centerline. Centerline
miles do not measure actual miles of pavement. For example, one centerline mile of a two-lane road would equal two
miles of pavement.
** Lane width already exceeds 80 percent goal
*** Pavement serviceability rating - the smoothness and pavement distress of a road segment with 40 representing
new pavement.
The remaining arterials make up another 15 percent of the mileage and carry 20 percent
of the traffic in the state. Because the arterial system carries a relatively small percentage of the statewide
traffic volume, MoDOT must adjust its investment in these routes
accordingly. Establishing a goal to meet 75 percent of the desired conditions on the remaining
arterials will result in more than twice the miles of good pavement on
this system while allowing MoDOT to use the majority of its funds to
address needs on the NHS.
Table
8
Highway Rehabilitation and Reconstruction Goals - Remaining
Arterials
(millions of dollars)
|
Attribute
|
Desired
Result
|
Mileage
Meeting Desired Result *
75% Target
|
Cost
to Achieve
Desired
Result
(2000
dollars)
|
|
Pavement
|
PSR** greater than or equal to 31
|
1,497 (31%)
|
3,621
|
$
1,626
|
|
Lane Width
|
12' travel lane
|
2,165 (45%)
|
no
goal established
|
126
|
|
Shoulder
|
8' - 10' hard surface
|
1,062 (22%)
|
no
goal established
|
222
|
|
Total
|
|
$1,974
|
* Centerline miles - Centerline miles do not measure actual miles of pavement. For example, one centerline mile of a two-lane road would equal two
miles of pavement.
** Pavement serviceability rating - the smoothness and pavement distress of a road segment with 40 representing new pavement.
The collector system, with 72 percent of the miles, carries 18 percent of the traffic in
the state. Shoulder and lane width improvements account for nearly 75 percent of the total collector
system needs. However, using the same principles applied to address needs on the arterial system, it
is more practical for MoDOT to target its investments at rehabilitation
and reconstruction and improvements needed to ensure safety on the
collector routes. Maintaining the road surfaces will protect MoDOT's investment. Targeting roads where traffic volumes exceed 1,700 vehicles per day
will benefit the most users.
Table
9
Highway
Rehabilitation and Reconstruction Goals - Collectors
(millions
of dollars)
|
Attribute
|
Desired
Result
|
Mileage
Meeting Desired Result
Current 70% Target
|
Cost
to Achieve
Desired
Result
(2000
dollars )
|
|
Pavement
|
PSR***** greater than or equal to 30
|
15,336 (66%)
|
16,266
|
$983**
|
|
Lane Width***
|
12' travel lane
|
853 (4%)
|
no
goal established
|
215
|
|
Shoulder****
|
2' - 8' aggregate surface
|
12,446 (54%)
|
no
goal established
|
175
|
|
Total
|
|
$1,373
|
* centerline miles - miles of highway measured
down the centerline. Centerline
miles do not measure actual miles of pavement. For example, one centerline mile of a two-lane road would equal two
miles of pavement.
** pavement cost based on average of $50 million
per year for 10 year overlay cycle.
*** shoulder width estimates based on assumption
that improvements made on routes with > 1,700 average annual daily
traffic count.
**** lane width estimate based on assumption that 10 percent of total goal would be set aside for lane width improvements.
***** Pavement serviceability rating - the smoothness and pavement distress of a road segment with 40 representing new pavement.
The
elimination of all bridges where condition ratings fall below 5 (on a
scale from 1 - 9) cannot be achieved using existing funding. Cost estimates for bridges were categorized based on the
corresponding roadway system (NHS, remaining arterials and collectors.) It is reasonable to set the same goals for bridges of 80
percent at a desired condition rating of 5 on the NHS and 75 percent at a
desired condition rating of 5 on remaining arterials and collectors. The
higher standard for collector system bridges is appropriate to ensure
continued safety of the traveling public. Once a bridge falls below condition 3, it must be closed.
Tables 10-12
illustrate the rehabilitation and reconstruction targets for the various
parts of the bridge system.
Table
10
Bridge Rehabilitation and Reconstruction Goals - NHS
(millions of dollars)
|
Attribute
|
Desired
Result
|
Number
of Bridges that
Meet
Desired Result
Currently 80% Target
|
Cost
to Achieve
Desired
Result
(2000
dollars)
|
|
Single-Condition Rating, Posted Load, width restricted and
vertical clearance
|
Greater than or equal to 5, legal load
limit, approach roadway width, legal vertical minimum
|
1,823
|
2,322
|
$1,583
|
|
Total
|
$1,583
|
Table
11
Bridge Rehabilitation and Reconstruction Goals - Remaining
Arterials
(millions of dollars)
|
Attribute
|
Desired
Result
|
Number of Bridges that
Meet Desired Result
Currently 75% Target
|
Cost to Achieve
Desired Result
(2000 dollars)
|
|
Single-Condition Rating, Posted Load, width restricted and
vertical clearance
|
Greater than or equal to 5, legal load
limit, approach roadway width, legal vertical minimum
|
758
|
1,133
|
$ 915
|
|
Total
|
$915
|
* Divided facilities with only two lanes of traffic in each direction will be considered adequate if the median shoulders are four feet or more.
Table
12
Bridge Rehabilitation/Reconstruction Goals - Collectors
(millions of dollars)
|
Attribute
|
Desired
Result
|
Number
of Bridges that
Meet
Desired Result
Currently 75% Target
|
Cost
to Achieve
Desired
Result
(2000
dollars)
|
|
Single-Condition Rating, Posted Load, width restricted and
vertical clearance
|
Greater than or equal to 5, legal load limit, approach roadway width, legal vertical minimum
|
1,609
|
4,133
|
$3,379
|
|
Total
|
$3,379
|
* Divided facilities with two lanes of
traffic in each direction will be considered adequate if the median
shoulders are four feet or more.
|