Project 7

Shannon/Carter Counties

UNDER CONSTRUCTION

Project Location

 

Project Update:

This project was awarded by the Missouri Highways and Transportation Commission in August.

This project was let in July 2007.

This project is included in the 2008-2012 Statewide Transportation Improvement Plan (STIP). The STIP was approved by the Missouri Highways and Transportation Commission (MHTC) during the July meeting.

Project Information:

Location: Route 19 to 3.5 miles east of Route J in Carter County
Length:
15.4 miles
Description: Project includes grading, paving, and bridges for a dual divided highway

Contractor: Chester Bross Const. Co./CB Equip. Inc., Hannibal Mo.
Project Cost: $36,379,847.99
Construction Began: September 2007
Construction Complete: October 2009

   
   