Project Update:
Complete: Oct. 2007
This project was awarded by the the Missouri Highways and Transportation Commission (MHTC) in Jan. 2007.
This project was let for bidding in Dec. 2006
|
|
Project Information:
Location:
Section 1: Route C to 1.2 miles east of Route M
Section 2: .5 miles east of Route 21 South to .8 miles east of Route B
Length:10.78miles
Description: Thin-lift asphalt resurfacing
Contractor: Pace Construction Company, LLC, St. Louis, Mo.
Project Cost: $1,293,600
Construction Begin: September 4, 2007
Construction Complete: October 24, 2007 |