December 22, 2004
Hollister/U.S. 65 Interchange Construction
Update for Week of December 27

 
*DISTRICT 8, SPRINGFIELD - Work scheduled: Rock blasting planned east side of U.S. 65 near Route 165.

Rock blasting planned at Birch Road and Industrial Boulevard.

Dirt graded and utilities relocated on east side of U.S. 65 along Business 65 near First Street.

Water and sewer lines installed on either side of U.S. 65 at Birch Road.

Impact on Traffic: When blasting occurs, traffic on U.S. 65 will be stopped for short periods before and after the blast. The scheduled delay for blasting is five minutes each time, though it could be longer. Blasting may occur several times a day.

One-lane traffic and delays possible at intersection of Birch Road and Industrial Boulevard.

All other work planned should take place AWAY from traffic.

Early Heads Up: Night work planned beginning the week of Jan. 3. Traffic stopped at night for short periods on Business 65 east of U.S. 65. Trucks hauling rock and dirt from northside of the road to south side.

Work zone speed limit on U.S. 65: 45 mph.

Project background: Construction of U.S. 65/Business 65 interchange and overpass for Business 65 north of new interchange and widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet north of Bus. 65/Route V to just south of Route 165.)

Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister and Taney County.

Prime contractor: W.A. Ellis Construction of Independence.

Scheduled completion: Fall 2006.


   
   