Route 30 and Geyer/Sappington Barracks Safety Project

What's going on now?
MoDOT will install a signalized intersection at this location after resident comments were receieved during a public meeting January 15, 2008 at the Mehlville Fire House #5, 11020 Mueller Road, St. Louis, MO 63123.
This safety improvement project is expected to begin late July 2008 and is expected to be completed in December 2008.
What is the problem with this intersection?
Route 30 at Geyer Road/Sappington Barracks is considered a hazardous intersection due to the number of crashes occurring at this location. MoDOT received inquiries about possible safety improvements to the intersection from local residents and performed a traffic study.
In the traffic study, two options were identified that addressed maintaining traffic flow in the area as well as reducing crashes at the intersection. The public supported installing a signal at Route 30 at Geyer Road/Sappington Barracks.
What is the timeline for this project?
- Jan. 15- Public meeting held
- Summer 2008- Construction begins
- Winter 2008- Construction completed
Additional information:
Who Do I Contact For More Information?
Contact MoDOT Project Manager Shirley Norris at 1-888 ASK MODOT (275-6636) or e-mail Shirley.Norris@modot.mo.gov
Contact MoDOT Area Engineer Kristy Yates at 1-888 ASK MODOT (275-6636) or e-mail Kristy.Yates@modot.mo.gov
Contact MoDOT Community Relations Specialist Jack Wang at 1-888-ASK-MODOT (275-6636) or e-mail Jack.Wang@modot.mo.gov